- 
Abbreviated as [WBS
 - 
Subdivide large tasks into smaller ones.
- Cannot estimate without dividing into distinct units
 
 - 
Everyone does it unknowingly.
 - 
It’s also an important element of project planning, so there’s a lot of consideration being given to it.
- Example: There are procedure-type WBS and deliverable-type WBS in WBS
 
 - 
History
- PMI introduced it to the public in PMBOK in 1987, after it was used by the U.S. Department of Defense and NASA.
 - In Japan, DIPS Intellectual Productivity System talks about task breakdown in 1992
- Not hierarchical.
 
 
 
Nishio’s tips on how to create an organized WBS
- 
For example, many people probably write down “things to do” in the form of a GTD Inbox or a TODO list (if you haven’t, do it first).
 - 
Often, “Vague and large tasks” that “cannot be started immediately” are mixed in among them.
- Example: “Write an explanation of how to solve the traveling salesman problem with a quantum computer.”
 - To perform this work, we need to break it up (i.e., break it down) into smaller pieces
 
 - 
Some may divide it up somehow.
- Example
- Write an explanation of how to solve the traveling salesman problem with a quantum computer.
- A brief description of quantum computers
 - Explanation of the traveling salesman problem
 - Explanation of what kind of Ising model should be used
 
 
 - Write an explanation of how to solve the traveling salesman problem with a quantum computer.
 - Another example
- Write an explanation of how to solve the traveling salesman problem with a quantum computer.
- A quick look at Reference X
 - Make a sticky note with excerpts of what you think you might need.
 - Put them together and come up with a story.
 
 
 - Write an explanation of how to solve the traveling salesman problem with a quantum computer.
 - The former is a deliverable-type WBS and the latter is a procedure-type WBS
 - If you have the extra capacity, you can make both and check them against each other to reduce omissions.
- In the above example, the procedure WBS is supposed to look at the reference material and think about the story, but the deliverables WBS has a tree that assumes that the story has already been decided, which is strange.
 
 
 - Example
 - 
The purpose of creating a WBS is not to divide tasks.
- The goal is to be able to perform a task, and the task is divided as a means to achieve this goal.
 - So once you get to a size where you can execute it, you don’t have to divide it any further.
 - The more detailed the division, the higher the management cost. It is necessary to master this sense of balance.
 
 
Notes before ----- summary: -----
- 
Task division skills improve as you repeatedly create a WBS.
- Typical patterns are clarified → WBS standard
 - By referring to it, oversight and lack of development can be avoided.
 
 - 
Able to clarify the scope of work
- What is written is what you do, what is not written is what you don’t do.
 
 - 
trick
- 
Make it with the intention of asking someone else to do it for you.
- I’m a stranger tomorrow.
 
 - 
(1) >The only advantage Excel has over project management tools is its initial ease of use.
- When the number of cases exceeds 100, it becomes unmanageable.
 
 - 
Writing Method
- Approx. 100 pieces
 - Vague task titles are not good.
- Detail down to about the title of the document that will be the output.
 - Structure elemental deliverables (what you make) as a guide
 
 
 - 
At first, we are not aware of deadlines.
- Adjustments are made only after the ideal plan is in place, ignoring deadlines.
 - There is no way the ideal plan will meet the deadline.
 
 - 
Proper attention to dependencies.
- Do not optimize anything but the critical path
 
 - 
Clarify who is in charge
 - 
Progress is measured by deliverables, not time frames.
 - 
WBS is not built by one person.
 - 
WBS detailed to a level that works effectively is information overload for the customer
 
 - 
 - 
WBS consists of levels and elements
- 100% rule: all child elements add up to equal the parent element
- Check to see if there are any leftovers.
 
 
 - 100% rule: all child elements add up to equal the parent element
 - 
There are two patterns of elemental decomposition: decomposition into objects and decomposition into work.
 - 
The leaves are called work packages.
 - 
8/80 rule: break down into elements until the work package is approximately 8 hours or more, but no more than 80 hours.
- One day to two weeks, that is.
 
 - 
7 x 7 rule: The number of child elements hanging from one parent element is limited to about 7, and the overall WBS level is limited to about 7 levels.
- The first level is one at the top level, so with 7 child elements and up to 7 levels, we can get to 117649 terminations.
 - Personally, I think adding a limit on the number of pieces is a streak evil, but it’s practically a limit.
 
 - 
Work decomposition type WBS
- A WBS of all the work required for the project
 - Also called project scope
 - Phase → task → work procedure… and it becomes a work manual style.
 - Easy to drop into schedule
 - The conditions for the completion of each task are unclear.
 - Different people have different images of the scope of work and
 - Risky to use a work breakdown WBS in a lump sum contract.
 - Potential to overlook necessary deliverables.
 
 - 
Outcome-decomposed WBS
- A WBS of all deliverables that are essential to complete
 - Also called product scope
 - Scope of responsibility is clarified.
 - Image of physical manufacturing divided into parts
 - WBS Workshop, published by PMI.
- Recommended because it is easier to define the scope of responsibility and the conditions under which the work will be completed.
 
 - Need to know deliverables in advance.
 - May overlook work needed for intermediate products
 
 - 
hybrid
- Create both a work decomposition WBS and a deliverable decomposition WBS
 - Compare in order from the top level and check for omissions
 
 - 
WBS is a tool for improving the efficiency of routine work
- 
About 10% of non-routine work
 - 
Efficiency by making 90% of the work routine.
 - 
Problems with [to-do list
 - 
Checks for omissions do not work.
 - 
Information that was in your working memory when you wrote it is lost, and you lose the details of the task.
- What are we doing this for?”
 - What exactly are we doing?”
 - Act as if notes for specific tasks are independent tasks
 - That would make me unmotivated.
 
 - 
TODO lists are suitable for small tasks with no dependencies between lines, where one line completes one task.
- Not suitable for “projects” that consist of multiple tasks or are large enough to span multiple days
 - WBS handles it in a tree format.
 
 
 - 
 - 
Rule: Make it top-down.
- why?
 - Is it true that “bottom-up” means leakage?
- Even top-down, you’re going to get leaks.
 - People make mistakes even when they intend to be MECE.
 - Wouldn’t it be more harmful to do it top-down and think “it’s top-down, so there are no leaks”?
 
 - rebuttal
- The importance of having both top-down and bottom-up perspectives Theory
 - List as many as you can think of, then organize them into a tree after the fact.
 - Note that the deliverable and work perspectives are mixed when created in a bottom-up manner.
 
 
 - 
Save the WBS you created for reuse.
- Gantt chart
 - Create in parallel with WBS of procedures and WBS of deliverables
 - Sticky only work packages.
 - Thinking side by side according to dependencies, etc.
 
 - 
First, get the big picture.
- With two WBS
 
 - 
Next, fill in from the hips.
- Parable of the Dishwasher
- After you start washing dishes, you realize there is no place to put them.
 - First we should think “let’s wash the dishes”, “washing the dishes means wetting, scrubbing, and dusting”, and “there is no place to dust”.
 
 - If you fill in from the deadline and the critical path is not met, that’s not possible.
 - Non-critical may be done at any time within the constraints
 - Not all tasks need to specify start and end dates and times
 - Estimates of duration should be clearly stated.
- Train your own estimating skills by seeing how the final estimate deviated.
 
 
 - Parable of the Dishwasher
 - 
References
 
This page is auto-translated from [/nishio/Work Breakdown Structure](https://scrapbox.io/nishio/Work Breakdown Structure) using DeepL. If you looks something interesting but the auto-translated English is not good enough to understand it, feel free to let me know at @nishio_en. I’m very happy to spread my thought to non-Japanese readers.